Maharashtra Proposes Phased Mumbai Airport Redevelopment to Prevent International Flight Disruptions
Maharashtra Chief Minister Devendra Fadnavis has proposed a new phased redevelopment strategy for Chhatrapati Shivaji Maharaj International Airport (CSMIA) in Mumbai. The plan aims to modernize the airport's ageing Terminal 1 (T1) while keeping existing flight operations running and avoiding the temporary transfer of international flights to Navi Mumbai International Airport.
The proposal focuses on building replacement facilities before demolishing the existing terminal. This approach is expected to reduce passenger inconvenience, prevent flight cancellations, and maintain Mumbai's international air connectivity during construction.
Mumbai Airport Terminal 1 to Be Rebuilt in Phases
In a letter to the Union Civil Aviation Ministry, Fadnavis suggested changing the construction sequence proposed by Mumbai International Airport Ltd (MIAL).
Under his proposed plan, the airport operator would first construct Terminal 1B and make it ready for operations. Flights currently operating from Terminal 1A could then move to the newly developed facility. Once the transfer is complete, the existing 1A structure could be demolished and rebuilt.
This approach would allow construction work and regular airport operations to continue at the same time, reducing the need to relocate flights during redevelopment.
Maharashtra Seeks to Avoid Shifting International Flights to Navi Mumbai
The proposal comes amid concerns from international airlines about MIAL's earlier plan to move some international flight operations to Navi Mumbai International Airport during the redevelopment period.
The airport operator had initially planned to begin shifting international services on October 25, 2026. However, the deadline was postponed to March 2027 following objections from foreign airlines.
The proposed transition involves moving flights on 14 international routes to Navi Mumbai to manage capacity limitations at Mumbai airport during construction.
The Maharashtra government has suggested an alternative that would allow these international services to continue operating from Mumbai without major interruptions.
Airlines and IATA Raise Concerns Over the Transition Plan
The proposed flight transfer has led to discussions between airport authorities and airline representatives. Representatives from more than 35 airlines recently met Mumbai airport officials to discuss the redevelopment schedule and operational arrangements.
The International Air Transport Association (IATA) has also supported a phased redevelopment approach, highlighting the importance of maintaining sufficient airport capacity throughout the construction period.
Keeping flight operations stable is important for passengers, airlines, and Mumbai's position as a major international aviation hub.
New Mumbai Terminal 1 to Increase Passenger Capacity to 20 Million
The redevelopment is also expected to improve the airport's infrastructure and passenger-handling facilities.
Mumbai's existing Terminal 1 was commissioned in 1964. Structural assessments conducted by Structwel in 2017 and the Indian Institute of Technology Bombay in 2024 raised concerns about the ageing facility.
The proposed replacement terminal is expected to increase annual passenger-handling capacity from 15 million passengers per annum (MPPA) to 20 MPPA.
Key improvements are expected to include:
- Modern passenger processing facilities.
- Improved security screening systems.
- Better passenger movement and circulation.
- Upgraded supporting airport infrastructure.
- Greater capacity to manage growing passenger demand.
The new terminal is targeted to become operational by March 2029, according to the PTI report.
What Happens Next With Mumbai Airport Redevelopment?
The phased construction proposal is expected to be considered by the Union Civil Aviation Ministry and MIAL. Further discussions will involve airport authorities, international airlines, and other stakeholders.
The final construction sequence and flight arrangements have not yet been approved. The proposal also does not confirm the cancellation of the previously planned international flight transfers.
If accepted, the approach could help Mumbai airport complete its modernization while protecting existing flight connectivity and reducing disruption for passengers.
The main objective is to ensure that Mumbai continues serving domestic and international travelers efficiently while its ageing Terminal 1 receives much-needed infrastructure upgrades.